it is very helpful to find some extra power capacity in the facity by wisely using load balancing data center power. when we have 3 phase UPS suppies installed in datacenter, they end up plugging into a power panel in such a way that doesn't maximize potential for UPS. they plug too many connection in one phase and other phase are underutilized.
if for phase A,B and C load is 150, 50 and 10 amps then it mean i need to work on my load balancing and move some power from phase A to B and C.
|