I would think about contacting a structural engineer. The battery weight issue is very common in data centers. A good structural engineer can develop a detailed scope of work for reinforcing the floor. Once you have this document you won't need to rely on the advice and counsel of the contractor that is doing the job. You can send the scope of work to a number of contractors and choose the one that comes back with the best offer.